DRAWER #18 106 EFFECT REPORTS & ASSESSMENTS OF ACTION


DRAWER #18 106 EFFECT REPORTS & ASSESSMENTS OF ACTION

1987

Rehabilitation of Wills Farmhouse (January)
Replace McPherson Fencing (January)
Repairs to Cinder-block Connector, Silo, Farm #3 (February)
Install Water Line, ENHS (February)
Replace Klingel Fencing (February)
Preservation Maintenance Barn Feeder, Farm #3 (February)
Preservation 1st Minnesota Monument Obelisk (March)
Preservation 1st Minnesota State Monument (Statue) (March)
Preservation Loafing Barn, Farm #2 (March)
Removal of Lean-to, Spangler Carriage House (March)
Preservation 1st Minnesota Memorial Urn (March)
Preservation Bushman Smoke (Pump) House (March)
Preservation Doubleday Statue (March)
Remove Underground Tanks (March)
Preservations ENHS Game Bird House (March)
Install Slyder Fencing (March)
Replace Gutters & Downspouts, ENHS Automatic Feeder (March)
Preservation & Equestrian Statues (6XXX's) (March)
Preservation Maternity Barn (March)
Preservation Loafing Barn, Farm #3(March)
Preservation Maintenance, North & South Feeders, Farm #3 (March)
Replant Ziegler's Grove (April)
Spangler Farmhouse (April)
Install Drain Tiles, Leister Orchard (July)
Install Paling Fence, Culp Farm (July)
Fill & Grade Camp Colt Swimming Pool (July)
Preservation Maintenance, EISE Farm #3 Barn (July)
Install Water Line, Cobean and Blocher Farms (July)
Underground Electrical Lines Spangler Farm (July)
Underground Power Lines, McPherson Farm (August)
Rebuild South Foundation Wall, Spangler Summer Kitchen (August)
John Gibbon Monument (September)
Trostle Farmhouse Preservation (September)
Preservation of Peace Light Memorial (September)
137th & 149th New York Monuments (September)
73rd New York Monument (September)
Install Gas Heaters, ENHS Reception Center (October)
Install Fencing, Codori-Trostle Woods (November)
Install New Monument, Samuel Wylie Crawford (November)
Install Fencing, Trostle Woodlot (November)
Install Water Line Altohoff Farm (November)
Repair Masonry, B. Redding #3 House (November)
Trostle Farmhouse, Destructive Investigation & Preventative Maintenance (November)
Replace Metal Roof, Cobean Farmhouse Foyer (November)
Reshape Forney Drainage (November)
Rehabilitation Althoff House (November)
Preservation Maintenance, West Bull Shed (November)
Fill Six Wells (November)
High Water Mark 111th New York, 1st Pennsylvania Monuments (November)
Replace Fencing, P. A. & S. Small Field (November)
Install Culverts, McClean Farm (November)
Plant Shrubs, National Cemetery Wall/Taneytown Road (December)
Washington Street Garage Preservation (December)
Rebuild Retaining Wall, EISE Barbecue (December)
Preserve U. S. Regulars Monument (December)
Replace, Remove & Preserve Walks and Steps Eisenhower Farm #1 (December)
Preserve Skeet Range Structures (December)

1988

January

Preserve Frey Barn
Install Fencing, Munshower Field
Install Fencing, Patterson Farm

February

Oak Ridge Power Lines
Removal of stumps
Preservation of Monuments, Hancock Avenue

March

Removal of 1st Shot Cannon for Placement in Museum of the Civil War

April

Preserve Michigan Monuments
Stabilization of Trostle Barn

May

125th Anniversary Activities
Preservation 151th Pennsylvania Monument
Replace Fencing, ENHS Red Rock Road
Preserve North Carolina Monument
Relocate Fence from Earthworks, Hancock Avenue
Re-gasification of Peace Light Memorial

June

Fill/Level Drainage bottom, EISE Farm #3
Erosion Gully & Tile Line, Spangler Farm
Stabilize & Restore mcClean Barn
Reconstruct Waterway, Farm #3 Field Road
Install Drain Tile, Nevins Lane, ENHS
Remove/Replace Coster Avenue Fence

July

Preservation Maintenance G.K. Warren Statue
Preservation Maintenance 56th Ohio Monument

August

43rd North Carolina Monument
Removal of Lloyd Cromer house
Replace Deteriorated Visitor Center/Cyclorama Center Walkway
Preserve 90th Pennsylvania Monuments
Secure 1st Shot Cannon, Buford Monuments
Removal of Bollinger House

September

Replace Roof, Hummelbaugh Farmhouse
Preservation Maintenance 74th Pennsylvania Monument
Level Porch, Trostle Farmhouse
Preserve Arkansas Monument
Preserve South Carolina Monument
Johns Avenue Sidewalk
Preserve Alabama Monument
Preserve Maintenance & Interior Rehabilitation, Frey House
Preserve Vermont Monuments
Replace Siding & Framing, Farm #3 Loafing Shed

October

McClean Farm Fencing
Preservation maintenance, Pennsylvania Monuments

1989

January

Preserve 83rd Pennsylvania Monument

February

Preservation Maintenance General John C. Robinson
Preservation Maintenance Hancock Equestrian Statue
Preservation Maintenance Florida Monument
Preservation Maintenance 53rd Pennsylvania Monument
Preservation Maintenance of the New York Monuments with Reliefs
Preservation Maintenance Texas Monuments

 

March

Removal of Furnay House
Replace McClean Picket Fence
Preservation Maintenance, Redding Farm #1 Bank Barn
Rehabilitation McMillan Woods Campground

April

ENHS Gardening Project:  National Trust of Scotland
Replace Bryan Orchard
Cobean Septic Field

May

Removal of Dwight Putnam House

June

Remove Sarah Singley House
Replace Window Frames at Cobean Farmhouse
Replace Rose Farmhouse Shutters
Preservation Maintenance Spangler House 
Preservation Maintenance Cobean House
Install Water Lines, Spangler & sherfy
Replace Fencing, Taneytown Road

September

Chimney Repairs, GNMP
Sale of Blocher House
Pitzer Farmhouse, ENHS #3 Preservation Maintenance & Septic
Windows, G. Weikert House

October

Remove Landscape Additions, Codori Farmhouse
Replace Nonhistoric Fence, Hancock Avenue with War Department Fence
Secure Cannon Tubes, Buford Monument
Preserve Spangler Smokehouse

November

Reattach Arm, 11th Massachusetts Monument

1990

January

Re-establish forest W. Confederate Avenue

Spangler Farm Erosion Gully (Re-run, edited)
Preservation/Maintenance Eisenhower House, Farm #1

February

Tree Screens--Herbst Farm & Maintenance Area
Hummelbaugh House & Fence
Maltese Cross, 22nd Massachusetts

March

Re-establish Fence Line, Hummelbaugh Farm
Re-establish Bliss Orchard
Stabilize/Restore Codori Garage
Rebuild Fence, Creep Feeder, Eisenhower #1

April

Preserve Althoff Summer Kitchen

May

Underground Utility Lines:  Rose, Bushman, Warfield/Wentz Farms
Preservation/Maintenance Bronze Monuments
Prserve Breeding & Equipment Shed
Preserve Culp House & Smokehouse
Replant Tree Screen & Flower Beds, National Cemetery
Preservation Maintenance, Hummelbaugh House
Replace Picket Fence, Trostle House
Install Septic Field, ENHS #1
Install Culverts & Waterway, Cobean Farm
Replace Picket Fence, Trostle Farm

June

Archeological Investigation, Bliss

July

Preservation maintenance, Farm #2 (Show Barn, Carriage House, Douglas Barn)

August

Install/Upgrade Security Systems, ENHS Farms
Re-roof Slyder Barn & Hog Pen
Two Monitoring Wells, Butterfield

September

Extend Access Road, Williams Quarry & Remove Buildings
Repair Slyder Windows
Replace Rail Fence, Sherfy Farm (Emmitsburg Road)

October

Roof Repairs, Cobean Farmhouse

November

Post & Board Fence, 1st Ohio Cavalry Monument, Taneytown Road
Bliss Orchard Fencing XXX
Cultural Resources Trip Reports